2021 Sidewalk Replacement Program

Project Name: 2021 Sidewalk Replacement Program

Project Start: October 18, 2021

Project Completion: October 27, 2021

Bid Price: $123,740 (subject to vary)

Project Summary

The 2021 Sidewalk/Curb Removal and Replacement Program was awarded to Schroeder and Schroeder Inc. at the October 5th Village Board Meeting. Construction is proposed to begin on October 20th and be substantially completed by October 27th – weather dependent.

New Sidewalk Installations

  • 336 W. Center Street (Food Pantry)
    1. Installation of approximately 140’ of new sidewalk in front of the Food Pantry (336 W. Center St.) that will connect existing sidewalks located to the east and west
  • 221-225 Catalpa Ave.
    1. Installation of approximate 45’ of new sidewalk to connect existing sidewalk to the north and south
  • 130 Forest Ave (Itasca Nature Center)
    1. Installation of approximately 240’ of new sidewalk around the mews and flight chambers

Sidewalk Replacements

Addressing trip hazards remains a priority during our annual sidewalk program. If you are aware of a trip hazard along Village sidewalks, please report them immediately to Public Works at 630-773-2455.

Deficient sidewalks that are not trip hazards, will be replaced based upon the level of deficiency and upcoming project locations as the budgeting allows.