Roadway and Infrastructure Project

Project Name: Roadway and Infrastructure Project - Phase 2

Project Start: April 1, 2023 (estimated)

Project Completion: December 31, 2023

Bid Price: $8,193,978.50

Contractor: John Neri Construction Company

Project Summary

The Roadway and Infrastructure Improvements- Phase 2 is a continuation of the Village’s curb and gutter program that was revitalized in 2022. Along with the addition of curb/gutter and sidewalks along the newly constructed roadways, improved drainage and new water main will also be installed. The exhibit below, indicates the planned areas of construction and the type of work that is planned.

The Phase 2 project consists of nearly 2.5 miles of new curb/pavement and 1.2 miles of new sidewalks within the project area. There will also be nearly 1.6 miles of storm sewer piping and 1.1 miles of water main installed during the project as well.

Roadway and Infrastructure - Phase 2 Map

  1. Construction Update – 2023 Roadway & Infrastructure Improvements – Phase 2 - Week of Nov 20, 2023

    During the week of November 20, 2023, the Contractor will be performing various restoration and clean up items on: Read on...
  2. Construction Update – 2023 Roadway & Infrastructure Improvements – Phase 2 - Week of Aug 28, 2023

    The Contractor will be watering sod during the week and on weekends, as necessary, depending on rainfall. Read on...
  3. Construction Update – 2023 Roadway & Infrastructure Improvements – Phase 2 - Week of Aug 14, 2023

    The Contractor will be applying prime coat and paving the final surface course on the above listed streets. We ask that cars not be parked on the following dates, daily from 7 am to 5 pm, Mon., August 14th and Tues., August 15th. Read on...
View All
  1. Phase 1 Description
  2. Phase 1 Project Documents

Project Name: Roadway and Infrastructure Project

Project Start: November 1, 2021

Project Completion: August 1, 2022

Bid Price: $5,238,896

Project Summary

DiMeo Brothers, Inc. has been awarded the contract to perform construction of the Roadway and Infrastructure Project. The project will consist of installation of new storm sewer, replacement of a water main, reconstruction of roadways to include curb and gutter along streets that do not currently have curb and gutter and resurfacing of streets in the project area that already have curb and gutter.

In an ongoing effort to improve the stormwater drainage throughout the community, the Village will be installing storm sewers in the area between North Street and Orchard Street and between Maple Ave. and Linden Street. There will be two main storm sewers that will be installed.  One main line will run along Elm Street from North Street to Orchard Street. The second main line will run along Center Street from Maple Avenue to Walnut Street, continuing south on Walnut Street and east along Orchard Street. This project will also include replacement of 80+ year old watermain along the streets that are to be reconstructed.

Completion of the storm sewer of this project will allow for systematic abandonment of an ancient common interest drain that currently runs in the rear yards of many properties between North Street and Orchard Street. 

NOTE: There will also be a separate Lead Water Service Line replacement program that will be done in conjunction with this project, where any water service lines along the project area that are determined to be made of lead will be replaced with service lines made of copper. Please visit the Lead Service Line Replacement Program project information for additional information.