Posted on: June 27, 2022
Traffic control barrels and signage will designate the one-way westbound direction. The one-way detour is anticipated to be in place for the duration of the project (through November 30, 2022).
The detour is required to facilitate the reconstruction of the...
Read on...
Bloomingdale Road Reconstruction Updates
Posted on: June 22, 2022
Traffic control barrels and signage will designate the one-way westbound direction. The one-way detour is anticipated to be in place for the duration of the project (through November 30, 2022).
The detour is required to facilitate the reconstruction of the...
Read on...
Bloomingdale Road Reconstruction Updates
Posted on: May 11, 2022
This morning, May 11, 2022, residents and Village officials woke up to find that a one-way westbound detour was set up on Bloomingdale Road overnight.
The contractor performed the work without prior approval causing a high level of frustration for both the...
Read on...
Bloomingdale Road Reconstruction Updates
Posted on: April 19, 2022
The project will consist of reconstruction and resurfacing of Bloomingdale consisting of pavement widening, installation of curb and gutter, storm sewer improvements, culvert improvements and stamped asphalt cross walks. A portion of Bloomingdal...
Read on...
Bloomingdale Road Reconstruction Updates