W. Division Street (N. Walnut Street to N. Oak Street)
Driveway interruptions will begin on Monday, August 28th on W. Division Street, between N. Walnut Street to N. Oak Street until driveway access is restored by 5 pm on Wednesday, September 13, 2023. During this time, curbs, driveway aprons, roadway base course grading and roadway asphalt to binder course will be placed to restore driveway access.
N. Maple Street (W. Center Street to W. North Street)
Due to extreme heat concrete curb and gutter placement was postponed. Therefore, driveway interruptions will continue on N. Maple Street, between W. Center Street and W. North Street, until driveway access is restored by 5 pm on Friday, September 8th. During this time, curbs, driveway aprons, roadway base course grading and roadway asphalt to binder course will be placed to restore driveway access.
Oak Street (W. Center Street to W. North Street)
Due to extreme heat concrete curb and gutter placement was postponed. Therefore, driveway interruptions will continue on Oak Street, between W. Center Street and W. North Street, until driveway access is restored by 5 pm on Friday, September 8th. During this time, curbs, driveway aprons, roadway base course grading and roadway asphalt to binder course will be placed to restore driveway access.
W. Center Street (Catalpa Avenue to N. Maple Street)
Topsoil has been placed in the parkway. Sodding is scheduled for mid-September to allow parking on W. Center Street during reconstruction work on N. Oak, N. Maple and W. Division Streets.
During this work expect the following:
- All roads will be open to emergency vehicles.
- Utility work (ComEd, Nicor Gas, MCI, etc.) along the project area will be taking place throughout construction.
- Heavy Construction Equipment, material deliveries, material storage in parkways and construction noise will be present from 7:00 AM to 5:00 PM daily and at times until dusk.
- The construction will create dust and debris. The Contractor will work to minimize the impacts.
- Access to driveways, other than the driveway interruptions detailed above, may be briefly interrupted - Workers will inform residents of driveway interruption prior to its occurrence.
- Temporary truck staging is expected on roadways and adjacent streets.
- Please Use CAUTION in around the construction site.
- The schedule is weather dependent.
- Use caution at the protruding manhole frames surrounded by cushioned protector rings.
If you have any further questions, please contact our Public Works at (630) 773-2455 or the field engineer, Mr. David Barnas of Robinson Engineering, Ltd., at (224) 723-8801.