Construction Update – 2021 Cured-In-Place-Pipelining Program - Week of October 25, 2021

The Village of Itasca has contracted with Michels Pipe Services to clean, televise, and line designated sanitary sewers.  The crews have completed the initial cleaning of the sewers and dye testing the house service laterals in the 300 block of Willow Street to confirm active services. Final spot cleaning, televising and lining is scheduled to resume on November 1, 2021 when materials arrive at the site.

Below is a tentative schedule for the work.  Work may begin one day before or after the listed date:

Street Location
Limits
Scheduled Lining

S. Elm Street

Bloomingdale Rd. to Washington St.

11/1/2021

N. Willow Street

Center St. to Division St.

11/1/2021

S. Lombard Road

400 Block of S. Lombard

11/2/2021

S. Maple Street

George St. to Washington St.

11/2/2021

S. Cherry Street

Washington St. to Irving Park Road

11/3/2021

S. Cherry Street

Irving Park Road to Schiller St

11/3/2021

Parkside Easement

South 200 Block - Bonnie Brae to Parkside

11/4/2021

S. Home Avenue

George St. to Washington St.

11/4/2021

S. Home Avenue

Irving Park Rd. to Washington St.

11/4/2021

S. Bonnie Brae Ave.

Irving Park Road to Schiller St

11/5/2021

S. Emerson Ave.

Washington Street to Schiller Street

11/5/2021

 

The process of sewer cleaning uses water jetting equipment that may induce pressure changes within the sewer.  Below are several tips to help reduce any inconvenience during the scheduled work:

  • Keep the toilet seat covers down.
  • Loosen caps or plugs on any exterior sewer cleanouts.
  • Cover basement and first floor drains to prevent any backsplash.
  • If you experience any odors after the cleaning has taken place, make sure that pea traps have water in them by running your faucets or adding water.
  • You may be asked to avoid flushing your toilet and limit water use during the lining portion of the project

If you have any questions regarding the work in progress, please contact Michels at: (920) 579-9952

If you have any further questions, please contact our Public Works at (630) 773-2455 or the field engineer, Mr. David Barnas of Robinson Engineering, Ltd., at (224) 723-8801.

Facebook Twitter Email