News Center

Public Works

Posted on: June 14, 2021

Construction Update – DCEO Street Lighting Project - Week of June 14, 2021

Construction of the DCEO Street Lighting Project started last week.

Utility Dynamics has installed all of the light pole foundations along Catalpa Avenue and Bryn Mawr Avenue; and has completed approximately half of the light pole foundations along North Street this past week.

This coming week, the remainder of the light pole foundations are scheduled to be installed, along with pouring the electrical control cabinet pads on Bryn Mawr Avenue and North Street.  Unit Duct cable installation is also scheduled to start mid-week along Catalpa Avenue. The Unit Duct will be installed by directional drilling to minimize the disturbance of the parkways.  Unit Duct installation will then proceed on Bryn Mawr Avenue and North Street once the installation on Catalpa Avenue is complete.

 

Temporary lane closures and delays may be experienced; however, they will only last for a short period of time during the construction operations.  

 

We ask for your full understanding and cooperation during construction.

 

If you have any questions, please contact our Public Works at (630) 773-2455 or the field engineer, Mr. Rob Borchering of Robinson Engineering, Ltd., at (708) 473-8068.