The Contractor will grind W. Center Street, between N. Willow Street and Catalpa Avenue, including the intersection of W. Center and Catalpa Avenue, on Wednesday, August 3rd, in preparation for resurfacing. Flaggers will be directing traffic to the work area. The Contractor will prepare asphalt driveway aprons for asphalt placement. Asphalt transition ramps will be placed
between the existing road and the ground road surface. The parkway and areas adjacent to the driveway aprons will be graded for future topsoil placement. Asphalt driveway aprons will be placed the week of August 14th
E. North Street (N. Linden Street to N. Rush Street) and N. Linden Street (E. North Street to E. Division Street)
Access to driveways will be interrupted from 7 am, Monday, July 24th, through 5 pm on Friday, August 4th. The driveway interruption is extended due to weather and scheduling. The asphalt base and binder course will be placed to allow residents to access their driveways by 5 pm on Friday August 4th,
Elm Street (Bryn M a w Avenue to E. North Street)
The Contractor will grind the roadway at the intersection of N. Elm Street and E. North Street, on Wednesday, August 3rd, in preparation for resurfacing. Flaggers will be directing traffic at the work area. Asphalt transition ramps will be placed between the existing road and the ground road surface. The Contractor will place topsoil in the parkway on Thursday, August 3rd and Friday, August 4th
N. Maple Street (W. Center Street to W. North Street) No work is scheduled until the week on August 21St. Oak Street (W. Center Street to W. North Street)
The Contractor will excavate for the new roadway and place an aggregate road base. The section
between W. Center Street and W. Division Street is expected to be closed to through traffic and
emergency vehicles on a daily basis from 7 am to 5 pm from Monday, July 31st through Tuesday, August 8th.