Construction Update – DCEO Street Lighting Project - Week of June 21, 2021

Over the past week, Utility Dynamics has completed the installation of all of the light pole foundations along North Street. Installation of cable and roadway crossings has begun along the south portion of Catalpa Avenue.

This coming week, the contractor will continue the installation of the Unit Duct cable and roadway crossings along Catalpa Avenue, Bryn Mawr and North Street. Temporary lane closures and delays may be experienced; however, they will only last for a short period of time during the construction operations.  

We ask for your full understanding and cooperation during construction.

If you have any questions, please contact our Public Works at (630) 773-2455 or the field engineer, Mr. Rob Borchering of Robinson Engineering, Ltd., at (708) 473-8068.