Check back regularly for updates on IL Route 390 / Elgin O’Hare Western Access construction through and around Itasca. All work is weather dependent. Drivers should continue to watch for changing traffic patterns, milled surfaces, uneven pavement levels, and traffic shifts. Use caution at all times. Sign up to receive these updates by email or text.

Weekly Construction Updates


  The new flyover ramp bridge connecting eastbound I-290 to eastbound IL Rt. 390 is now open to traffic, creating a new free-flow movement within the I-290 Interchange. It is expected that the new free-flow ramp will eliminate bottlenecks and significantly reduce travel delays on IL Rt. 390 and through the interchange with the elimination of the last remaining traffic signal at the interchange controlling traffic flow between eastbound I-290 and eastbound IL Rt. 390.

Please use caution while driving in construction zones. On IL Rt. 390 a 45 mph work zone speed limit is in effect throughout the construction season. Work zone speed limits are in place on other roads in the project area as well, including a 55 mph work zone speed limit on I-290. The minimum penalty for speeding in a work zone is $375. Posted signs advise drivers of a $10,000 fine and a 14-year jail sentence for hitting a roadway worker. 

 
Please be advised, the newly constructed ramp from eastbound I-290 to eastbound Illinois Route 390 is scheduled to open in a one lane configuration at 1 a.m. on Tuesday, November 29. The left lane will remain closed to be opened at a later date. In conjunction with the ramp opening, the traffic signal at the existing intersection of the ramp from eastbound I-290 to eastbound Illinois Route 390 will be removed. Additionally, third lane on westbound Illinois Route 390 between Hamilton Lakes Drive and I-290 will be opened.
  
On Tuesday, October 25 at 8:00 pm, traffic from IL 390 and from the I-290 ramp to EB IL 390 will be shifted to allow the Tollway to commence construction of the elevated proposed eastbound IL 390 pavement. Please use caution while driving in this area.

Also, Clover Ridge Lane is scheduled to reopen to traffic on Thursday, October 27 at 5:00 pm, ending the detour. 

Starting Wednesday, October 12, 2016, Rohlwing Road will be reduced to one lane in each direction between Thorndale Avenue and Hamilton Parkway for pavement patching for about two weeks. Also, the eastbound and westbound IL 390 Frontage Roads will be reduced to one lane between Meacham and Rohlwing Roads for pavement patching for the two week period from 10/12/16 to 10/31/16. 
 
Over the next week there will be several lane closures and a traffic shift in the Elgin O’Hare Western Access Corridor. Traffic shifts September 22 at 9 a.m. on westbound Thorndale Ave from west of Mittel Drive to Prospect Ave. The two westbound lanes of traffic will be shifted to the old eastbound lanes. This traffic shift will remain until mid-October. During this stage of construction storm sewer, water main and portions of the Prospect Ave intersection will be constructed.
Daytime lane closures begin at 6 a.m. September 22 with one right lane closed on westbound Thorndale Avenue between Larsen Lane and Thomas Drive for trucking access. The eastbound right lane will close at 9 a.m. also for trucking access. Work should be completed by 4 p.m.
Nighttime lane closures begin at 7 p.m. September 22 with one right lane closing on eastbound I-290 between Devon Ave and south of Thorndale Ave for bridge deck formwork. A second right lane will close at 9 p.m. All lanes will reopen by 5 a.m. on Friday, September 23.
Nighttime closures continue on September 23 at 8 p.m. with one left lane closed on eastbound I-290 between Devon Ave and south of Thorndale Ave for bridge deck formwork. A second left lane will close at 10 p.m. One lane will reopen by 9 a.m. on Saturday, September 24 and all lanes will reopen by 11 a.m.
Next week on Monday, September 26, one right lane on westbound I-290 between south of Thorndale Ave and Devon Ave will close at 7 p.m. for bridge deck formwork. A second right lane will close at 9 p.m. All lanes will reopen by 5 a.m. on Tuesday, September 27. On Tuesday night, September 27, one left lane on westbound I-290 between south of Thorndale Ave and Devon Ave will close at 7 p.m. A second left lane will close at 9 p.m. All lanes will reopen by 5 a.m. on Wednesday, September 28.
All work is weather dependent. Please use caution when driving in work zones.

Clover Ridge Lane from Thorndale Avenue to the furthest west leg of Miller’s Crossing will be closed starting Tuesday, September 27 for 2-3 weeks. Electronic message board and detour signs are being installed by the Illinois Tollway to direct traffic. Please see this map for detour information.

All work is weather dependent. Please use caution when driving in work zones. 
http://www.itasca.com/DocumentCenter/View/7004
  
Starting on Friday evening around 11 pm, there will be a significant traffic pattern change on the Elgin O’Hare. Westbound traffic will begin to move onto the mainline, and the westbound ramp to IL Rt. 390 from Ketter Drive will open for use. http://www.itasca.com/DocumentCenter/View/6995

Please drive with caution in work zones. 

Please be aware that this weekend there will be a significant traffic pattern change on the Elgin O'Hare east of Arlington Heights Road. Eastbound Elgin O'Hare/Thorndale Avenue traffic between Arlington Heights Road and Rt. 83 will be temporarily routed onto the new frontage roads and portions of the mainline.

Depending on weather, the transition to the new traffic pattern will begin on Friday, August 26 at 9 pm and is planned to be complete by 1 am Saturday morning. The new traffic pattern will be in place for the Monday, August 29 AM Rush hour.

Use caution in this area.
http://www.itasca.com/DocumentCenter/View/6983     new routes

Lane and ramp closures with detours are scheduled to begin this weekend on I-290 and continue throughout August for construction of a new Illinois Route 390 Tollway bridge over I-290.  Full Details : http://www.itasca.com/DocumentCenter/View/6982


The right westbound lane on Illinois Route 390 between Park Blvd and the I-290 intersection is scheduled to close at 11 p.m. on Tuesday, August 9. At 1 a.m. the ramp from westbound Illinois Route 390 to westbound I-290 will close with a posted detour. This closure will allow the point of entry for the westbound Illinois Route 390 to westbound I-290 ramp to be moved further west on Illinois Route 390. This work is being done so that the construction on this ramp can continue. The ramp will reopen by 5 a.m. on Wednesday, August 10 and the right lane on westbound Illinois Route 390 will reopen by noon. 

  
Please take note of the following lane and ramp closures this weekend. The right westbound lane on Illinois Route 390 between Park Blvd and the I-290 intersection will close at 11 p.m. on Saturday, July 30. At 1 a.m. Sunday morning, the ramp from westbound Illinois Route 390 to westbound I-290 will close with a posted detour. The ramp will reopen by 7 a.m. on Sunday, July 31 and the right lane on westbound Illinois Route 390 will reopen by noon.

Use caution while driving in work zones.

Starting early on Saturday, July 23 at 3:00 am, all traffic on Thorndale Avenue will be reduced to one lane in both directions. During this time, no left turn movements will be allowed onto Prospect due to the required work zone. Traffic will be moved back to 2 lanes in each direction later in the weekend.

On Monday, July 25, single lane closures on westbound Thorndale will occur and left turn movements may be restricted temporarily throughout the morning. The single-lane closures will be completed by about 1:00 pm that day.

Please use caution while driving in work zones.

Weather permitting, the newly re-aligned Parkside Avenue will be opened to traffic on Friday, July 1. This will likely occur in the am hours. The new alignment only allows a right in-right out access to/from Arlington Heights Road. 
Please remember that electronic tolling begins on the western portion of IL Rt.390/Elgin O’Hare on Tuesday, July 5. The portions of the expressway east of I-290 will not be tolled. 

 On Wednesday, June 22, at 3 p.m. traffic lanes will shift on Prospect Ave to the west between Granville Rd and south of Pierce Rd. One lane of traffic will remain open in each direction with northbound and southbound left turn lanes open at the intersection of Thorndale Ave. This traffic shift will remain in this configuration until mid-August. During this stage of construction storm sewer, sanitary sewer, the east portion of Prospect Ave and portions of the new eastbound and westbound Illinois Route 390 bridge will be constructed. All work is weather dependent. 

On Thursday, June 16, one westbound lane on IL Rt 390 between Park Boulevard and I-290 is scheduled to close at 9 pm to prepare for a traffic shift on the ramp connecting westbound IL Rt 390 to westbound I-290. At 1 am on Friday, June 17, a full ramp closure is scheduled and traffic will be detoured via the Meacham Road loop ramp to eastbound IL Rt 390 and back to the I-290 Interchange where traffic will be able to exit to westbound I-290. All lanes are scheduled to reopen by 5 a.m. on Friday, June 17, ahead of rush hour traffic.

Electronic message signs and construction signage will be put in place in advance to alert drivers to the overnight closures and detour. The temporary closures are necessary to provide a work zone and safely accommodate the construction of the I-290 Interchange. All work is weather dependent. 
   


On Saturday, June 11 from 6 am to 8 pm., one right lane on eastbound Thorndale Ave between Park Blvd and Arlington Heights Road will close for beam delivery and storage. Nicole Way at Thorndale Ave will close with a posted detour at 6 a.m. as the beams will be staged across Thorndale Ave in this location. Nicole Way and the right lane on eastbound Illinois Route 390 will reopen by 6 p.m. 

 Also, a portion of Arlington Heights Road between Thorndale Ave and Pierce Road and a portion of Ketter Drive between Arlington Heights Road and Pierce Road will also close at 6 a.m. with a posted detour for beam installation. Ketter Drive and Arlington Heights Road will reopen by 8 p.m. A right westbound lane on Ketter Drive between Arlington Heights Road and Pierce Road will remain closed until noon on Monday, June 13. 
    
Please note, a portion of Parkside Avenue in Itasca will be permanently closed starting tomorrow, Thursday, June 2, at 7:00 a.m., as the local road is realigned as part of the Illinois Route 390 Tollway Project. The northern portion of Parkside Avenue currently connecting to Thorndale Avenue will be removed to accommodate new ramps and frontage roads for local traffic. When work is complete, Parkside Avenue will be realigned to connect to Arlington Heights Road. Drivers will be able to access the new frontage roads and the new Illinois Route 390 Tollway from Arlington Heights Road when construction is complete by the end of 2017.

A detour will be posted until the realignment of Parkside Avenue is complete. All work is weather dependent. 


On Thursday, May 12, from 4-7 p.m., the Illinois Tollway will host an open house at the Elk Grove Village Hall, 901 Wellington Avenue. The open house will provide information about 2016 construction of the new Illinois Route 390 Tollway and answer questions about cashless tolling scheduled to begin July 5 on the completed portion of the new roadway between I-290 to Lake Street (U.S. Route 20).

http://www.illinoistollway.com/documents/10157/a4a7a897-3c9c-4541-98d7-56e8d32863b4



Please be advised that the traffic lights at Park Boulevard and Hamilton Lakes Drive, north of Thorndale Avenue, have been temporarily turned off and replaced with stop signs. Northbound traffic on Hamilton Lakes Drive from Thorndale Avenue will not have a stop sign in order to prevent back up onto Thorndale. Southbound Hamilton Lakes Drive and eastbound Park Boulevard will have stop signs at this intersection.

Please note that Clover Ridge Lane/Park Boulevard between Prairie Circle and Willow is scheduled to be closed to traffic on Friday, April 29 from 7 a.m. to 7 p.m. to install portions of the sound wall. If a second day of work is needed, or if weather does not cooperate, the alternate closure date is Monday, May 2 from 7 a.m. to 7 p.m. Please note, that if a second day of work is needed, the roadway will be opened over the weekend – there will not be a continuous closure from Friday into Monday. Detour signage will be posted

 On Sunday, April 17th, traffic lanes on eastbound I-290 between Devon Avenue and Irving Park Road will shift to the inside (left) lanes. On Monday, April 18th, traffic lanes on westbound I-290 will then shift to the inside (left) lanes. The lane reconfiguration on both nights will begin around 7 p.m. and the traffic shifts will be completed by 5 a.m. the next day. This configuration will last for about 6 weeks. During this time, the acceleration lanes on I-290 are being constructed.

Please use caution while driving in work zones and obey posted speed limits.

Please note that on Wednesday, April 13, at 8:00 p.m. traffic in each direction on Prospect Avenue between Granville Road and Pierce Road will be shifted to the east, with one left turn lanes in both directions open at the intersection of Thorndale Avenue.

Traffic is expected to remain in this configuration until the end of June. This work is being done to accommodate a new bridge for IL Rt. 390 over Prospect Avenue and an interchange at this intersection. All work is weather dependent. 
 

  
Please note that on Monday, April 11, traffic in each direction on Prospect Avenue between Granville Road and Pierce Road will be shifted to the east, with one left turn lanes in both directions open at the intersection of Thorndale Avenue. Traffic is expected to remain in this configuration until summer. This work is being done to accommodate a new bridge for IL Rt. 390 over Prospect Avenue and an interchange at this intersection.

On Wednesday, April 13, Tollway contractors will be installing beams on the bridge that will carry eastbound I-190 ramp traffic to eastbound IL Rt. 390. One left lane on westbound IL Rt. 390 between Prospect Avenue and Rohlwing Road will close at 9 pm. All lanes on westbound Elgin O’Hare between Park Ave and Rohlwing Road along with the westbound IL Rt. 390 ramp to eastbound I-290 will close from midnight to 5 a.m. on Thursday, April 14 with a posted detour. All lanes will reopen by 5 a.m. on Thursday, April 14. Similar closures with posted detours will occur as needed until May 8, 2016, and more information will be posted in the future.

All work is weather dependent. 
 
 
Please note, the portion of Prospect Avenue north of Arlington Heights Road between the Elk Grove Bank and Top Golf/Salt Creek Golf Club will be closed for utility work from around 7 pm Friday night through about 4 am on Monday morning. Detour routes will be posted and access to the golf course, bank, and other businesses will be open.  
Please note that starting around 9 a.m. tomorrow morning Prospect Avenue between Granville Avenue and Thorndale Avenue will be down to one lane in each direction. All lanes and turn lanes at the intersection of Prospect Ave and Thorndale Avenue will remain open. This configuration will be in place until for about 2 weeks, weather permitting. Please use caution in this area.  

Weather permitting, overnight lane and roadway closures are scheduled for Monday, March 7th on Hamilton Lakes Drive for bridge beam installation as part of construction of Illinois Route 390 over Hamilton Lakes Drive.

Hamilton Lakes Drive will be closed to traffic overnight with a posted detour. Lane closures are scheduled to begin at 4 p.m. with one northbound lane closing, followed by closure of all lanes in both directions at 7 p.m. During the roadway closure, traffic will be detoured via East Pierce Road, Ketter Drive, Arlington Heights Road and Thorndale Avenue. Turn lanes from Thorndale Avenue onto Hamilton Lakes Drive will also be closed. All lanes are scheduled to reopen by 7 a.m. the following morning.

Electronic message signs are being put in place in advance to alert drivers to the overnight closures and the posted detour. Should weather not cooperate, contingency dates are Tuesday, March 8th or Wednesday, March 9th, if needed. 
 
 

Because of the lack of advanced notice for the motoring public, the proposed traffic control has been moved a week back to the week of 2/29 and will last through the end of March.
Starting next week through the end of February, Park Boulevard between Hamilton Lakes Drive and Pierce Road will be reduced to one lane in each direction by shifting all traffic to the north side of the existing median. Temporary left turn restrictions within the work zone may be in place during this time. Please reduce speeds and use caution.  

Please be aware that temporary, overnight lane closures on I-290 are scheduled this weekend to install new roadway signage for the I-290 Interchange Project. In addition, the ramps carrying Biesterfield Road traffic to eastbound I-290 and eastbound I-290 traffic to Illinois Route 390 are scheduled to close and a detour will be posted. Electronic message signs will be put in place in advance to alert drivers to the overnight closures.

Weather permitting, overnight work is scheduled to begin Saturday, February 13, including intermittent, full closures of eastbound I-290 lasting no longer than 15 minutes, for roadway signage installation. Three eastbound lanes on I-290 between Higgins Road and Illinois Route 390 and one westbound lane between Biesterfield Road and Illinois Route 390 are scheduled to close at midnight for work to prepare for signage installation. Intermittent, full closures of the eastbound lanes are scheduled between 1 a.m. and 7 a.m. on Sunday, February 14, on eastbound I-290. All lanes will reopen by 8 a.m.

In addition, the ramps carrying Biesterfield Road traffic to eastbound I-290 and eastbound I-290 traffic to Illinois Route 390 are scheduled to close from 1 a.m. to 7 a.m. Detours will be posted.

Traffic on Biesterfield Road wishing to travel east on I-290 will be detoured onto westbound I-290 and directed to exit at Higgins Road before reentering I-290 headed east.

Traffic on eastbound I-290 wishing to exit to westbound Illinois Route 390 will be directed to exit at Biesterfield Road and then detoured via Rohlwing Road, Nerge Road and Meacham Road to Illinois Route 390. Traffic wishing to exit to eastbound Illinois Route 390 will be directed to exit at Biesterfield Road and then detoured via Rohlwing Road, Devon Avenue and Prospect Ave to Illinois Route 390. 
 

  
Starting tomorrow, Friday, November 13th at 4:30 am, asphalt paving operations will be taking place on Arlington Heights Road, north of Thorndale Avenue, which will involve flagger control lane closures.  The contractor will be grinding the southbound, outside lane near on Arlington Heights Road at  Ketter Road, followed by paving work to meet the final paving operations for Ketter Road reconstruction from the Jewel Building to Arlington Heights Road.  Arlington Heights Road north of Thorndale Avenue will be impacted for a majority of the working day tomorrow.  All work is weather permitting. 

Please note that Arlington Heights between Thorndale and Pierce Roads will be closed starting Friday, October 30th at 10 am through Monday, November 2nd at 10 am for utility work related to the Elgin O’Hare. Use Prospect Road as an alternate route. Detour signage will be posted. 
 
Work will start on Devon Ave October 21 and continue through next week. Temporary daily lane closures will be set up in each direction for the work. No work will start before 9 am for the east bound lanes and work should be completed by 3 pm
The main work involves the construction of a 2” expansion joint in the concrete pavement for the entire width of the roadway. At this time there is no plan for a concrete patch which should allow the roadway to be opened to all lanes at the end of each day 
 
Important Closure Notice: Beginning at midnight on Monday, October 12, Park Boulevard/Clover Ridge Lane will close with a posted detour for installation of a box culvert. The street is planned to be closed for 10 calendar days and is scheduled reopen by 11:59 p.m. on Wednesday, October 21, weather permitting. It is the Village’s understanding that local residents on Miller’s Crossing and Wildspring Court will have access to those street via Park Boulevard/Clover Ridge Lane. Residents on Prairie Court and Willow Street will need to use the detour route of Arlington Heights Road and Bryn Mawr Avenue. 


Beginning at midnight on Friday October 2, Arlington Heights Road between Thorndale Avenue on the north and Theodore Lane on the south is set to close with a posted detour. The closure will be 3 calendar days in duration and will reopen by 11:59 p.m. on Sunday, October 4. 
Map 
/DocumentCenter/View/6591

Sept 25 Reminders! Please note the Rohlwing Road Bridge Traffic Shift that is occurring today. One lane of traffic on the bridge will be open in each direction. Please use caution with the new lane configuration. The Bridge is scheduled to fully open on Thursday, October 15.

On Monday night, after the PM rush hour, the eastbound lanes on Thorndale Avenue will shift to the left and the westbound lanes will be reduced to one through lane and shifted to the right between Nicole Way and Prospect Avenue. The left turn lane from eastbound Thorndale to northbound Arlington Heights Road will be CLOSED. Detour signage will be posted.

Sept 18
- Please note the following upcoming lane configurations related to the Elgin O’Hare / IL Rt. 390 Construction Project:

Rohlwing Road Traffic Shift
Starting in the early morning hours of Thursday, September 25th, both sides of the Rohlwing Road/IL Rt. 53 bridge over the Elgin O’Hare will be open. One lane of traffic will be open in each direction. Traffic will be shifted to the inside lane between W. Thorndale Ave and transition to the outside lane over Rohlwing Rd Bridge. Traffic will stay in the outside lane between the westbound Frontage Rd and Devon Ave. Landscape, electrical work, temporary pavement removal and median work will occur during this stage. Traffic will remain in this configuration until Thursday, October 15 at 5 p.m. when all lanes will open on Rohlwing Road, weather permitting.

Thorndale Avenue between Nicole Way and Prospect Avenue
On September 28 at 8 p.m., the eastbound lanes on Thorndale Avenue will be shifted to the left and the westbound lanes will be reduced to one through lane and shifted to the right between Nicole Way and Prospect Ave. The left turn lane from eastbound Thorndale Avenue to northbound Arlington Heights Road will be CLOSED. Detour signage will be posted 
  
Aug 27 - The outside lane and shoulder of southbound Prospect Avenue from Thorndale Ave to Granville Avenue will be closed.  The schedule is to reopen the southbound Prospect Avenue outside lane and shoulder on Friday, September 4.

Aug 24 Starting tonight Monday, August 24 at 8:00 pm and ending Tuesday, August 25 in the early morning hours, the eastbound, outside lane of Thorndale Avenue between Park Boulevard and Prospect Avenue will be closed. The temporary lane closure will be taken down by rush hour traffic on Tuesday.   



Aug 19 Overnight full roadway closures of the Elgin-O’Hare/IL Rt. 390 between Roselle Road and Meacham Road in Roselle are scheduled with detours for the weekend of August 22. Electronic message signs and detour signage will be put in place to alert drivers in advance of the closure and detour. Beginning at 9 p.m. on Saturday, August 22, one left eastbound lane between Roselle Road and Meacham Road will close to prepare for the full closure and detour. All eastbound lanes will close at 10 p.m. and traffic will be detoured. One left lane will reopen by 6 a.m. on Sunday, August 23. All lanes will reopen by 7 a.m. A similar closure and detour are scheduled for the westbound lanes on Sunday, August 23. All lanes will reopen by 7 a.m. on Monday, August 24.

Also, starting on Wednesday, August 26, there will be a lane closure on Prospect Avenue south of Thorndale. Where there are 2 lanes, the southbound outside lane will be closed for sewer work on the shoulder. Northbound lanes will not be impacted. Work is scheduled to be completed and the lane reopened by Friday, September 4. Prior to the scheduled lane closure, a temporary lane closure is expected to happen this Thursday evening and be completed by rush hour Friday morning in preparation for the scheduled work

Aug 3 - Work in this immediate area will continue through next weekend with temporary closures as follows: Today through Thursday, 8/13 , Park Boulevard north of Thorndale Avenue between Fifth Third Bank and the new Hamilton Lakes Drive is and will be closed to traffic. Hamilton Lakes Drive is open to traffic from Thorndale Avenue to Pierce Road to allow access to Fifth Third Bank, the Westin, and other businesses along Park Boulevard in Hamilton Lakes.

On Friday, 8/7, Park Boulevard north and south of Thorndale Avenue will close to traffic at Thorndale Avenue with the same detours as this past weekend. Lane closures will occur in the eastbound lanes of Thorndale Avenue pushing traffic into one lane westbound and one lane eastbound at Park Boulevard. Detours will be posted on all segments. Park Boulevard north to the new Hamilton Lakes Drive and south of Thorndale is scheduled to reopen the early morning of Monday, 8/10.

All work is weather dependent.



July 28 - Starting at 9 pm Friday, July 31 through Monday, August 3 at 6 am, Park Boulevard north of Thorndale Avenue will be closed to traffic between east of Fifth Third Bank to North of Thorndale Avenue. Park Boulevard south of Thorndale Avenue will be closed to traffic at Thorndale Avenue. The Westbound (WB) Thorndale lanes will be closed and transitioned into one lane westbound and one lane eastbound, through work zone west of Park Boulevard. Residents south of Thorndale Avenue on Park Boulevard will follow posted detour route which will require travel south to Bryn Mawr Avenue to Arlington Heights Road to Thorndale Avenue. If traveling to Hamilton Lakes will continue travel north to Ketter Drive and follow posted detour.

On Monday morning, Park Boulevard north of Thorndale Avenue will be closed to traffic between east of Fifth Third Bank to the west edge of the newly constructed Hamilton Lakes Drive. New Hamilton Lakes Drive will be open to northbound and southbound traffic from Thorndale Avenue to Pierce Road. Park Boulevard south of Thorndale Avenue will reopen to traffic. Thorndale Avenue will be fully open to traffic with no lane reductions.

All work is weather dependent. Map


July 24 - Beginning Friday night, July 24, crews will work over the weekend to open the several new ramps to traffic, including the flyover ramp from westbound I-290 to westbound Illinois Route 390 and the ramp from eastbound I-290 to westbound Illinois Route 390, creating new, free-flow traffic movements to the west and eliminating the signalized intersection at Thorndale Avenue. A new ramp from westbound I-290 to eastbound Illinois Route 390 will also open in time for the morning commute on Monday, July 27. Please use caution on the new ramp configurations

June 30 - Starting Wednesday, July 1 through Monday, July 15, there will be overnight lane closures in I-290 between Biesterfield Road and Thorndale Avenue for the construction of bridge girders. There will also be closures on the ramps to and from IL Rt. 390 and I-290. Lane closures are expected to begin about 7 p.m. Full intermittent stops are expected to occur between 1 a.m. and 5 a.m. on weekday mornings and 1 a.m. and 7 a.m. on Sunday mornings. All lanes will reopen by 7 a.m. each morning.

Mid-week, Elgin O’Hare / IL Rt. 390 work within the Hamilton Lakes development will be suspended through the weekend for Itasca’s Fourth of July Fireworks display. Please note, however, beginning Wednesday morning portions of Ketter Drive and Pierce Road will be closed for fireworks setup and the event itself. Detour signage will be installed. The closure will remain in place until 8:00 a.m. Sunday morning. For more information on the Itasca Fireworks

Please have a happy and safe Fourth of July!




June 12 - Traffic on Thorndale east of I-290 has been snarled because of Com Ed utility relocation work. The existing closure of the eastbound left turn lane at Thorndale onto northbound Arlington Heights Road, will be re-opened on Saturday and the lane closures will be moved to the outside eastbound lane just west of Arlington Heights Road. This phase is anticipated to last one week with other phases to begin after the eastbound crossing is complete. This work was permitted by DuPage County.

June 5

The week of June 8 a portion of Clover Ridge Lane, west of Willow and adjoining the retention pond, will be closed for repaving by Tollway contractors. Work includes removal of temporary pavement, placement of permanent material, and lighting work. The closure is expected to last for about 2 weeks, depending on weather. As a result of this temporary road closure, all vehicle traffic must enter and exit the neighborhood via Bryn Mawr Avenue. This is the same detour route as last summer. Appropriate detour signage is being installed by the Tollway’s contractors.

June 1


Tonight there will be lane closures on I-290 related to the construction of the new ramp structure taking eastbound IL Route 390 traffic to westbound I-290. One westbound lane between Bloomingdale Rd and Thorndale Ave will close at 7 p.m. this evening. A second lane will close at 9 p.m., and a third lane will close at 11 p.m. Full intermittent (15 minute) closures will occur on westbound I-290 and the eastbound Illinois Route 390 ramp to westbound I-290 between 1 a.m. and 4 a.m. All lanes will reopen by 5 a.m. on Tuesday June 2.

Itasca Clover Ridge neighborhood residents please take note: the week of June 8 a portion of Clover Ridge Lane, west of Willow and adjoining the retention pond, will be closed for repaving by Tollway contractors. Work includes removal of temporary pavement, placement of permanent material, and lighting work. The closure is expected to last for about 2 weeks, depending on weather. As a result of this temporary road closure, all vehicle traffic must enter and exit the neighborhood via Bryn Mawr Avenue. This is the same detour route as last summer. Appropriate detour signage is being installed by the Tollway’s contractors.

Installation of the first all-electronic tolling gantries as part of the Elgin O’Hare / IL Route 390 project is scheduled to start next week with overnight lane closures on IL Route 390, west of I-290. Work to build the first 3 toll collection points is scheduled for 2015 in coordination with the completion of the first segment of the new roadway this year.

Work scheduled to begin next week and be complete this summer includes installation of tolling gantries in each direction at each of the 3 locations on IL Route 390: west of Meacham Road/Medinah Road, west of Roselle Road, and west of Gary Avenue. The over-the-road steel tolling gantries are being installed now to accommodate testing and ensure that toll collection can begin within the first segment from Lake Street (U.S. Route 20) to I-290 in summer of 2016. Installation of the toll collection equipment is anticipated to begin as early as this summer and a sign stating “No Tolls Taken” will be posted on the tolling gantries until the toll collection begins.

Installation of 4 toll collection points east of I-290 will be complete by the end of 2017, and toll collection is expected to begin on the eastern segment of IL Route 390 by the end of 2017.

Altogether, all-electronic tolling gantries will be installed at 6 locations along IL Route 390 and on the Ketter Drive entrance ramp. Tolls for passenger vehicles will be 20 cents per mile for the 10-mile trip and range from 20 cents to 60 cents per transaction for I-PASS customers. The ramp toll at the Ketter Drive entrance in Itasca to westbound IL Route 390 will be 20 cents for I-PASS customers.

Passenger vehicles traveling the full length of IL Route 390 will pay $1.90, similar to the I-PASS toll paid to travel on I-355 south extension between I-55 and I-80. For more information view the Installation (PDF).


May 22


Next week in the evenings there will be lane closures on I-290 related to the construction of the new ramp structure taking eastbound IL Route 390 traffic to westbound I-290. The scheduled closures are as follows:

  • Tuesday, May 26 - One eastbound lane between Biesterfield Road and Thorndale Avenue will close at 7 p.m. on Tuesday, May 26, for beam erection. One westbound lane between Irving Park Rd and Thorndale Ave will close at 7 p.m. A second lane in both directions will close at 9 p.m., a third eastbound lane will close at 11 p.m. and a fourth eastbound lane will close at midnight. Full intermittent (15 minute) closures will occur on eastbound I-290, the eastbound I-290 exit ramp to Illinois Route 390 and the westbound Illinois Route 390 ramp to eastbound I-290 between 1 a.m. and 5 a.m. All lanes will reopen by 5 a.m. on Wednesday, May 27.
  • Wednesday, May 27 - One eastbound lane between Biesterfield Rd and Thorndale Ave will close at 7 p.m. on Wednesday, May 27, for beam erection. One westbound lane between Irving Park Rd and Thorndale Ave will close at 7 p.m. A second lane in both directions will close at 9 p.m., a third eastbound lane will close at 11 p.m. and a fourth eastbound lane will close at midnight. Full intermittent (15 minute) closures will occur on eastbound I-290 and the westbound Illinois Route 390 ramp to eastbound I-290 between 1 a.m. and 5 a.m. All lanes will reopen by 5 a.m. on Thursday, May 28.
  • Thursday, May 28 - There is a contingency if the work is not completed on Wednesday, May 27. The closure, if needed, would be the same as May 27.
  • Saturday, May 30 - One westbound lane between Bloomingdale Rd and Thorndale Ave will close at 8 p.m. on Saturday, May 30, for beam erection. A second lane will close at 10 p.m., and a third lane will close at midnight. Full intermittent (15 minute) closures will occur on westbound I-290 and the eastbound Illinois Route 390 ramp to westbound I-290 between 1 a.m. and 7 a.m. One lane on westbound I-290 will reopen by 8 a.m. on Sunday, May 31, a second lane will reopen by 10 a.m. and all lanes will be reopened by 1 p.m.

May 14


Resurfacing on Devon Avenue at the bridge over I-290 is currently ongoing, resulting in the closure of 1 lane in each direction during the day. This work should be completed by the middle of next week, depending on weather.
 
The work in the Hamilton Lakes development is moving along quickly, leading up to the Highland Games on June 19 and 20. For more information on the Highland Games


May 7


Traffic-realignment continues in the Pierce Road and Ketter Drive area beginning the morning of May 13 and scheduled for completion June 17.

Traffic on East Pierce Road between Windsor Drive and Arlington Heights Road and Ketter Drive between East Pierce Road and Arlington Heights Road will be switched to the eastbound lanes as resurfacing and median removal begins on the westbound lanes.

In both cases 1 lane of traffic will be maintained in each direction. As always this schedule is weather dependent.

Remember: motorists are required by law to turn on headlights when operating the wind shield wipers or during low-light conditions.

May 1


Depending on weather, resurfacing on Devon Avenue at the bridge over I-290 is planned to begin next week. This work on the pavement directly east and west of the bridge deck, will result in the closure of 1 lane in each direction during the day. It is expected to take up to 5 days. Some weather reports are currently calling for rain next Monday and Tuesday. This may postpone Devon Avenue paving until later in the week and push it into the week of May 11.

The work in the Hamilton Lakes development is moving along quickly with curbs and gutters being installed in the next few weeks. Drivable pavement on Pierce Drive and Ketter Road by June 17, leading up to the Highland Games on June 19 and 20.

As a reminder, cell phone use is prohibited while driving in a highway construction zone.

April 15


Traffic-realignment was completed today on Pierce Road and Ketter Drive. Please slow down and use caution in this area.
In the next 2 weeks, resurfacing on Devon Avenue at the bridge over I-290 is expected to begin. The Devon Avenue Bridge was replaced last summer as part of Elgin O’Hare construction to allow more room under the bridge from entrance/exit ramps to/from I-290. The remaining pavement work east and west of the bridge deck will close 1 lane in each direction. This work is expected to be complete by the end of May. Detailed information will be distributed as it becomes available.
As a reminder, cell phone use is prohibited while driving in a highway construction zone.

April 10


Traffic shifts on Pierce Road and Ketter Drive are planned to occur on Monday, April 13. Work is scheduled to begin at 7 a.m. on Monday, April 13. Pierce Road between Windsor Drive and Arlington Heights Road and Ketter Drive been Pierce Road an Arlington Heights Road will be reduced to 1 lane in each direction to begin reconstruction of Ketter Drive and resurfacing of Pierce Road. Traffic is scheduled to remain in this configuration through early May.

April 8


Elgin O’Hare Construction gets in full gear next week within the Hamilton Lakes Development. On Monday, April 13, all traffic on Pierce Road will move to a 2-lane configuration (1 lane eastbound, 1 land westbound). All traffic on Ketter Drive will also move to a 2-lane configuration (1 lane northbound, 1 lane southbound). The lane closures and shifts are for the re-surfacing and widening of Pierce Road, in preparation for the construction of the new Hamilton Lakes Drive and provide access to a future frontage road. The lane closures and traffic shift will have no impact on Park Boulevard.

Roadway has been signed in advance to alert drivers, and electronic message boards have also been added on Pierce Road to alert of pending work and related delays to traffic.

All construction is weather dependent. Please use caution while driving in construction areas.

March 13

Beginning this coming Monday March 16, 2015 for approximately 2 weeks, a ComEd contractor will close 2  lanes of eastbound Thorndale Avenue between Mittel Blvd. and Wood Dale Road with restricted ‘No Left Turn’ northbound movements onto Wood Dale Road at the intersection as they work on installing a utility duct package crossing of Thorndale Avenue. This is the 3rd phase of this 4 phase utility relocation work.

Advance warning digital message boards were posted earlier this week notifying motorists of the upcoming work and turning movement restrictions in this area.

Expect delays in this area. You may wish to seek alternate routes of travel.

February 2


Beginning this Wednesday for approximately 6-8 weeks, eastbound Thorndale Avenue at Wood Dale Road will experience extended land closures while a ComEd contractor installs utility ducts.
 

December 3


Contractors on IL Route 390 / Elgin O’Hare are finalizing some of the major construction for the season. All lanes on the Devon Avenue bridge over I-290 are scheduled to open next week. Median sections are now being replaced and final pavement striping in the construction zone will be occurring in advance of the bridge opening to full traffic. The new westbound ramp off of I-290 is schedule to open this Friday, December 5th.

Work on IL Route 53 / Rohlwing Road, including the southbound pavement and structure over the Elgin O’Hare will continue through the winter months. Some utility relocations in the Elgin O’Hare corridor will also continue through the winter months. These construction operations will be controlled by weather conditions.

November 20


The Illinois Tollway unveiled its tolling plan for Illinois Route 390. Through-trips for passenger vehicles will be 20 cents per mile for the 10-mile trip and range from 20 cents to 60 cents per transaction for I-PASS customers. The ramp toll at the Ketter Drive entrance to westbound Illinois Route 390 will be 25 cents for I-PASS customers. Passenger vehicles traveling the full 10-mile length of Illinois Route 390 will pay $1.90, similar to the I-PASS toll paid to travel on the Veterans Memorial Tollway (I-355) south extension between I-55 and I-80. Business rules and toll rates for commercial vehicles and customers who wish to pay cash are under development and will be announced next year.
 
Toll collection is expected to begin in 2016 for the first section of Illinois Route 390 from Lake Street (U.S. Route 20) to I-290. This scheduled for completion at the end of 2015. The second section from I-290 to Busse Road (Illinois Route 83) is scheduled for completion at the end of 2017, when toll collection for this section begins has yet to be determined.

November 14


In the late night hours of this coming Saturday, Sunday, and Monday, Tollway Contractors will be setting up a detour of Eastbound I-290 and Eastbound and Westbound Thorndale Avenue between Prospect Avenue and Meacham Road. The detours will begin after 11 p.m. The detours will end by 8 a.m. on Sunday morning and by 5 a.m. on Monday and Tuesday mornings. Detour signs will be in place. Please use caution.

November 6


Please Note Major Change in Traffic Pattern: The Rohlwing Road bridge over Thorndale Avenue / IL Route 390 was scheduled to open to traffic on Friday, November 7, 2014. This has now been delayed to occur overnight Saturday, November 8 in to the morning hours of Sunday, November 9. This means north-south traffic on Rohlwing Road will shift onto the new bridge, and the existing lanes on the east-side of Rohlwing Road (lanes are at-grade) will be eliminated. Norwood Avenue will also be re-opened to traffic. Please use caution is this area, as workers will be present, several of the traffic movements will be significantly different, and new temporary traffic signals will be is use.

November 4


Please Note Major Change in Traffic Pattern: The Rohlwing Road bridge over Thorndale Avenue / IL Route 390 is currently scheduled to open to traffic on Friday, November 7, 2014. This means north-south traffic on Rohlwing Road will shift onto the new bridge, and the existing lanes on the east-side of Rohlwing Road (lanes are at-grade) will be eliminated. Norwood Avenue will also be re-open to traffic. Please use caution is this area, since several of the traffic movements will be significantly different and new temporary traffic signals will be is use.

October 28


On Arlington Heights Road, near the Thorndale Avenue intersection, a contractor will be conducting soil borings on Thursday and Friday of this week. Intermittent, short-term closures on Arlington Heights Road are expected. Appropriate traffic control will be used. Please use caution when driving in this area and allow for short delays.

Reminder: Itasca residents are invited to attend an informational meeting hosted by the Village of Itasca tomorrow night (Wednesday, October 29) from 6:30 to 8 p.m. at the Itasca Holiday Inn, 860 W. Irving Park Road.

The purpose of the meeting is to discuss Elgin O’Hare improvements between Arlington Heights Road and Prospect Avenue, including construction, noise analysis update, and visual screening alternatives. Representatives from the Illinois Tollway project team will provide updated information and will be available to answer questions. Postcard invitations were mailed to property owners in the immediate vicinity.

October 20


Please note that starting at 10 p.m. this evening into the early hours of Tuesday morning, ComEd will be removing cables across I-290. This will result in lane closures on I-290, and full closure of I-290 in 15 minute increments between 1 and 3 a.m. The ramp from eastbound Thorndale Avenue to northwestbound I-290 will close at midnight. The ramp from Biesterfield to southeastbound will also close at midnight. State police forces will be directing traffic. All lanes and ramps are scheduled to reopen by 4 a.m. on Tuesday.

Itasca residents are invited to attend an informational meeting hosted by the Village of Itasca on Wednesday, October 29 from 6:30 to 8 p.m. at the Itasca Holiday Inn, 860 W. Irving Park Road. The purpose of the meeting is to discuss Elgin O’Hare improvements between Arlington Heights Road and Prospect Avenue, including construction, noise analysis update, and visual screening alternatives. Representatives from the Illinois Tollway project team will provide updated information and will be available to answer questions. Postcard invitations were mailed to property owners in the immediate vicinity.

September 29


Night-time lane reductions on southeast bound I-290 were planned for Saturday night. However, IDOT was unable to provide the necessary state police assistance and that work was cancelled. The work is now planned to take place this evening, Tuesday evening, and, if necessary, Wednesday evening.

Please plan for southeast bound I-290 near the Devon Avenue bridge to be reduced to 1 lane over several hours starting at 7 p.m. Full lane closures may also occur in the early morning hours from 1 a.m. to 5 a.m., for a maximum of 15 minutes at a time with state police directing traffic. Also the ramp from Biesterfield to southeast bound I-290 will close at 12 a.m. After the work zone, all lanes will be open.

All work is weather dependent. Please consider using alternative routes.

September 23


Questions have been raised by Village residents about why no soundwall is being proposed along the Elgin O’Hare Expressway between Prospect Avenue on the east and Arlington Heights Road on the west. In July, the Village wrote a position letter to the Illinois Tollway outlining the Board’s desire for a soundwall. At tonight’s Village Board meeting at 7 p.m. at the Itasca Village Hall, the Village’s consultant, Scott Marquardt of HR Green, will be providing information on the Tollway’s response to date, and the Village will work to set up a future public information meeting on the topic. More info to come!

As a reminder, work on the Devon Avenue bridge over I-290 will result night-time lane reductions on I-290 tomorrow night, Thursday, and Saturday. On Wednesday and Thursday, northwest bound I-290 near the Devon Avenue bridge will be reduced to 1 lane over several hours. Full lane closures may also occur in the early morning hours from 1 a.m. to 5 a.m., for a maximum of 15 minutes at a time with police directing traffic. The ramp from eastbound Thorndale to Northwest Bound I-290 will also be closed at 12 a.m. After the work zone, all lanes will be open.

On Saturday, southeast bound I-290 near the Devon Avenue bridge will be reduced to 1 lane over several hours. Full land closures may also occur in the early morning hours from 1 a.m. to 7 a.m., for a maximum of 15 minutes at a time with police directing traffic. After the work zone, all lanes will be open.

All work is weather dependent. Please consider using alternative routes.

September 19


Please take note for next week, work on the Devon Avenue bridge over I-290 will result night-time lane reductions on I-290 on Wednesday and Thursday, September 24 -25 and Saturday, September 27. On Wednesday and Thursday, northwest bound I-290 near the Devon Avenue bridge will be reduced to 1 lane over several hours. Full lane closures may also occur in the early morning hours from 1 a.m. to 5 a.m., for a maximum of 15 minutes at a time with police directing traffic. The ramp from eastbound Thorndale to Northwest Bound I-290 will also be closed at 12 a.m. After the work zone, all lanes will be open.

Next week Saturday, southeast bound I-290 near the Devon Avenue bridge will be reduced to 1 lane over several hours. Full land closures may also occur in the early morning hours from 1 a.m. to 7 a.m., for a maximum of 15 minutes at a time with police directing traffic. After the work zone, all lanes will be open.

Please consider using alternative routes. All work is weather dependent.

September 15


Medinah Road / Meacham Road at I-390 / Elgin O’Hare Expressway will be closed intermittently (15-20 minute increments expected) from 8 p.m. Wednesday, September 17 to 6 a.m. Thursday, September 18. The closures is due to placement of structural beams for the bridge widening on the Elgin-O’Hare improvements. Advance warning digital message boards notifying motorists of the planned work have been posted.

Expect delays in your travels through this corridor. You may wish to seek alternate routes of transportation.

September 5


Sound walls along I-290 are being delivered and the new walls will start going up next week. If your property adjoins this area, please remember to remove items within the construction easement.

Weather permitting, Hamilton Parkway is scheduled to reopen the week of September 15th. Periodic night time closures during of Meacham / Medinah Road for the placement of beams will also occur the week of September 15th.

Looking ahead, on Rohlwing Road, traffic will switch to the new bridge in mid to late October.

August 20


ComEd will be implementing some maintenance improvements at the intersection of Rohlwing Road and Norwood late this morning into this afternoon. This work is not Elgin O'Hare related, but will impact the signal operations at the intersection. While ComEd has a back-up system that will be utilized, any failures of the backup system may cause delays.

Traffic has been transferred from the north side to the south side of the Devon Avenue Bridge and decorative fencing is being installed.

Sound wall replacement and construction along I-290 will resume next week with most of the replacement work kicking into full gear after the Labor Day weekend. Temporary fencing will be installed to restrict access onto the expressway.

On Thorndale Avenue, work will begin on a bridge over Salt Creek. Contractors have already started clearing the area along the creek.

August 13


A Tollway contractor will be crushing the existing stockpile of concrete that is located on the south side of Thorndale Avenue between I-290 and Park Boulevard. Specific dates and duration of the crushing work is not available at this time. The Village has advised the Tollway that the Village Ordinances on hours of operation will be strictly enforced during this activity.

Traffic on the Devon Avenue bridge over I-290 will move from the north side to the south side this Friday.

Norwood Avenue at Rohlwing Road is scheduled to close on Monday, August 18. All signs that can be installed in advance are up. The road will remain closed for a maximum duration of 45 calendar days. Also on Monday, August 18, work will re-start on the noise wall along I-290. This will consist of removal of section of the old noise wall, construction and grading of swales, installation of the new sound wall, and landscaping. The actual construction of the new noise wall will start no later than Monday, August 25.

A contract for the construction of a bridge over Salt Creek at Thorndale Avenue (to become the Elgin O’Hare) has been let. Work in this area is anticipated to start in 2 to 3 weeks.

All work is weather dependent.

August 13


Devon Avenue Bridge - A traffic shift is scheduled this week to move all traffic onto the newly reconstructed portion of the bridge carrying eastbound Devon Avenue traffic over I-290 as part of the Elgin O'Hare Western Access (EOWA) Project.
 
On Friday, August 15, traffic in both directions will be shifted onto the eastbound side of the Devon Avenue Bridge so work can begin to prepare for the removal and reconstruction of the westbound side.

Reconstruction of the Devon Avenue Bridge is needed to accommodate the new I-290 Interchange at Illinois Route 390. The new, 4-lane bridge is scheduled for completion by the end of the year. Up to 25,200 vehicles a day use the Devon Avenue Bridge.

As Devon Avenue Bridge construction continues, traffic on Devon Avenue between Rohlwing Road and Bay Drive will remain reduced to 1 lane in each direction. Three lanes of traffic on I-290 will remain shifted to the outside shoulders, however bridge removal will require some temporary, overnight lane closures on I-290.

The public can follow the progress of the work on the Devon Avenue Bridge and other work on the EOWA Project via camera images offering birds-eye-views on the Illinois Tollway’s website www.illinoistollway.com. Views of ongoing work along Illinois Route 390 are updated every 15 minutes and available online.

August 6


Clover Ridge Lane is now temporarily closed at Park Boulevard. All vehicle traffic must enter and exit the Clover Ridge neighborhood via Bryn Mawr Avenue. Detour signage has been installed.

Traffic on the Devon Avenue bridge will move from the north side to the south side on Friday, August 15.

Norwood Avenue at Rohlwing Road is scheduled to close on Monday, August 18. Appropriate detour signage will be installed by the Tollway’s contractors.

Also on Monday, August 18, work will re-start on the noise wall along I-290. This will consist of removal of section of the old noise wall, construction and grading of swales, installation of the new sound wall, and landscaping.

All work is weather dependent.

July 30


Thorndale Avenue in both directions between Park Boulevard and Rohlwing Road is scheduled to temporarily close tonight from about midnight until 5 a.m. in the morning. While weather dependent, this is the last planned closure of this roadway for the foreseeable future.

Thorndale will be open to through traffic for access to the residential subdivisions to the south and to emergency vehicles. Appropriate detour signage will be posted by the Tollway’s contractors.

As a reminder, Clover Ridge Lane will be temporarily closed at Park Boulevard West, near the northern-most Clover Ridge retention pond starting August 3, 2014. As a result of this temporary road closure, all vehicle traffic must enter and exit the neighborhood via Bryn Mawr Avenue. Appropriate detour signage will be installed by the Tollway’s contractors.

Norwood Avenue at Rohlwing Road is scheduled to close in mid-August. Additional information will be posted here as it becomes available.

Hamilton Parkway is currently closed at the far west end of the street. This area will be closed until the end of August.

In other IL Route 390 / Elgin O’Hare construction news, on the Devon Avenue bridge over I-290 traffic is expected to be moved from the north side to the south side in about 2 weeks. The Rohlwing Road bridge over the Elgin O’Hare is expected to open for traffic this fall and work will then start on the other side of the bridge. Overall, the Elgin O’Hare project is on-time through Itasca.

July 25


Thorndale Avenue in both directions will be temporarily closed between Rohlwing Road and Arlington Heights Road in the early morning hours Sunday from after midnight to 8 a.m. to move equipment. This same stretch of Thorndale is also scheduled to close Monday and Tuesday mornings from after midnight to 5 a.m. Appropriate detour signage will be posted by the Tollway’s contractors.

As a reminder, Clover Ridge Lane will be temporarily closed at Park Boulevard West, near the northern-most Clover Ridge retention pond starting August 3, 2014. As a result of this temporary road closure, all vehicle traffic must enter and exit the neighborhood via Bryn Mawr Avenue. Appropriate detour signage will be installed by the Tollway’s contractors.

Norwood Avenue at Rohlwing Road is scheduled to close in mid-August. Additional information will be posted here as it becomes available.

All planned road closures are weather dependent.

July 18


The road closure scheduled on Thorndale Avenue between Rohlwing Road and Arlington Heights Road in the early morning hours for Sunday, Monday and Tuesday nights has been canceled due to some technical difficulties with the equipment on the crane. Closures will be most likely the following week.

July 17


Thorndale Avenue in both directions will be temporarily closed between Rohlwing Road and Arlington Heights Road in the early morning hours Friday (tomorrow) from about 2 to 5 a.m. to move equipment. This same stretch of Thorndale is also scheduled to close Sunday morning from 1 to 7 a.m.; Monday morning from 1 to 5 a.m.; and Tuesday morning from 1 - 5 a.m. Appropriate detour signage will be posted by the Tollway’s contractors.

Clover Ridge Lane will be temporarily closed at Park Boulevard West, near the northern-most Clover Ridge retention pond starting August 3, 2014. As a result of this temporary road closure, all vehicle traffic must enter and exit the neighborhood via Bryn Mawr Avenue. Appropriate detour signage will be installed by the Tollway’s contractors. Notices to Clover Ridge property owners are being mailed by the Village.

Additionally, the Tollway Authority is hosting a meeting to discuss the Clover Ridge Lane Closure and to answer resident questions. The meeting will be held on Thursday, July 24, 2014 at 6:30 p.m. at the Itasca Village Hall, 550 West Irving Park Road, Itasca. The meeting will be open to the public and you are invited to attend.

Norwood Avenue at Rohlwing Road is scheduled to close in mid-August. Additional information will be posted here as it becomes available.

July 10


Work continues on Elgin O’Hare. Devon Avenue Bridge deck pour work is on schedule. Another contractor is setting the beams for the fly-over ramp from northbound I-290 to westbound Elgin O’Hare. Periodic delays on both the Devon Avenue bridge and Rohlwing Road at Thorndale Avenue are expected.

We have previously reports that Norwood Road at IL Route 53 will close for an extended period. However, this has been pushed back due to utility conflicts. No closure date has yet been finalized. It will be reported as soon as more information is known.

Village work in Hamilton Lakes is almost complete. The contractor is finalizing landscaping and street light work.

July 3


Elgin O'Hare construction will be suspended for the long Independence Day weekend.

Next week, the bridge deck for the Devon Avenue bridge will be poured. Traffic disruptions are anticipated, and you may wish to avoid this area starting Monday. Also next week, the contractor will begin installing beams for the I-290 northbound flyover ramp to westbound Elgin O'Hare.

Closure of Norwood Avenue has been delayed due to utility conflicts on Rohlwing Road. New dates for the closure of Norwood will be posted when information becomes available.

Have happy and safe 4th of July. Please don't drink and drive.

June 26


Over the next few weeks, the Village of Itasca expects that IL Route 390/Elgin O'Hare contractors will be periodically closing lanes on I-290 for beam placement. Hamilton Parkway closed last week, and no specific re-opening date is known at this time.

The road construction within the Hamilton Lakes development is nearing completion. Pavement markings and landscaping should be done next week. Some street lighting work will continue after July 7th. Thank you for your patience with this project!

June 19


Elgin O’Hare work is moving quickly and the Village has been told that the work to date is on time and within budget.

The west of end Hamilton Parkway will be closed tomorrow for approximately 3 months. The Tollway has coordinated closure with impacted property owners. Two other road closures are to occur in mid-July. Those are 1.) Norwood Avenue at IL Route 53 and 2.) Park Boulevard, south of Thorndale Road. The Village to try to provide notice of these closures via its website and the “Notify Me” service as soon as more detailed information becomes available. The Tollway is responsible for posting appropriate detour signage.

In the Hamilton Lakes development, roadwork on Park Boulevard, Pierce Road, and Windsor Drive will be suspended on Friday and through the weekend for the Highland Games.

June 11


The far west end of Hamilton Parkway in the Hamilton Commerce Center development is scheduled for temporary closure within the next week. Actual dates are not known at this time and updates will be posted as soon as possible. The Tollway is coordinating with property owners.

Also, please be aware that Norwood Road at IL Route 53/Rohlwing Road is scheduled to close in mid-July for about 40 days into late August. Detour routes will be signed.

The sidewalk along South Park Boulevard, between Willow and Clover Ridge subdivision, will be re-opened as soon as weather permits.
Within the Hamilton Lakes development, all paving work should be completed by the end of next week, weather permitting.

June 6


The work in the Hamilton Lakes area is progressing quickly. At Pierce and Windsor: The asphalt surface will be completed for Pierce Road on Monday.

The pavement marking contractor is scheduled for Wednesday. The new light poles will be delivered the last week in June and work will begin after the 4th of July weekend.

At Park Boulevard: Full depth patching will be completed today. Level binder will be placed Monday and Tuesday. The driveways will be done Wednesday and Thursday. At the end of next week new loops for the signals and finishing the concrete work will take place. Final surface may occur next Friday, but more likely the following week.
 
The signals at Park and Pierce no longer operate by the loops and are on recall.

June 6


Beginning on or after the morning of June 23 the removal of the existing timber noise wall on the east side of I-290 will commence. The new wall will be installed a short distance west of the existing wall. The duration from removal of existing wall to installation of the new wall will be no more than 14 days. Residents are asked to remove any personal property abutting or affixed to the existing wall prior to June 23.

June 5


Please be advised the construction and removal of the existing noise wall along I-290 has been delayed due to weather conditions.
The main beams for the Rohlwing Road Bridge across Thorndale were constructed this week. The contractor is still currently on schedule to have traffic on the west portion of the bridge this fall.

June 2


Thorndale Road will not be closed tonight. Thorndale Road in both directions at IL Route 53 / Rohlwing Road will be closed to traffic Tuesday night June 3, starting at 11 p.m.and ending Wednesday morning , June 4 at 5am. Traffic will be re-routed to IL Route 19 / Irving Park Road.

May 30


Please be aware, the scheduled Thorndale Road closures have changed again. Thorndale Road in both directions at IL Route 53 / Rohlwing Road will be closed to traffic on Saturday, May 30, 12 midnight until Sunday, June 1, 8 a.m. Thorndale will also be closed Monday June 2 midnight until Tuesday, June 3rd, 4 a.m. Traffic will be re-routed to IL Route 19 / Irving Park Road.

May 29


Please be aware, the scheduled Thorndale Road closures have changed. Thorndale Road in both directions at IL Route 53 / Rohlwing Road will be closed to traffic on Sunday, June 1st and Tuesday, June 3rd from about 12 a.m. to 5 a.m. in order to install large steel beams for the Rohlwing Road overpass bridge. Traffic will be re-routed to IL Route 19 / Irving Park Road.

May 28


As a reminder, subject to weather conditions both directions of Thorndale Road at IL Route 53 / Rohlwing Road will be closed to traffic on Thursday, May 29th and Saturday, May 31st from about 12 a.m. to 5 a.m. in order to install large steel beams for the Rohlwing Road overpass bridge. Traffic will be re-routed to IL Route 19 / Irving Park Road.

Also, on Thursday, May 29th in the morning after rush hour for approximately 30 minutes Thorndale Road between Park Boulevard and Arlington Heights Road will be reduced to 1 lane.

Along I-290, the Tollway has started removing existing sound walls and are now installing new soundwalls.

In Hamilton Lakes, on Pierce and Windsor the level binder course of asphalt will start on Thursday and final surface course is scheduled for next week. Please use caution for fresh oil. On Park Boulevard, the contractors will finish concrete work this week. Road grinding will end next week and paving will begin shortly thereafter.

May 22


Note: Subject to weather conditions, both directions of Thorndale Road at IL Route 53 / Rohlwing Road will be closed to traffic on Thursday, May 29th and Saturday, May 31st from about 12 a.m. to 5 a.m. Traffic will be re-routed to IL Route 19 / Irving Park Road. Rohlwing Road will open for north-south traffic. Detour Routing Signage (PDF)

Roadwork continues within the Hamilton Lakes development, on Pierce Road and Windsor Drive full depth asphalt patching and driveway binder coarse has started. Manhole adjustments being made after Memorial Day. On Park Boulevard, removal of curbing in certain areas will continue and new concrete poured. The contractor has coordinated driveway access with the various building managers.

May 19


One westbound lane of the Elgin O’Hare between Meacham and Roselle Roads will close from 6 a.m. to 2 p.m. on Tuesday, May 20, for lighting work and earth excavation. One eastbound lane of Thorndale Road at I-290 will close from 9 a.m. to 3 p.m. on Tuesday for electrical removal.

Within the Hamilton Lakes development, on Pierce Road and Windsor Drive full depth asphalt patching and driveway binder coarse will start on Tuesday, May 20 and should be completed by the end of the week. The level binder course will also likely begin late this week, with manhole adjustments being made after Memorial Day. On Park Boulevard, removal of curbing in certain areas will continue and new concrete poured. The contractor has coordinated driveway access with the various building managers.

May 14


Construction of new sound walls along I-290 is starting. Notifications to impacted residents will be provided next week with staff walking door to door to deliver flyers.

In the Hamilton Lakes area, grinding of Pierce Road and Windsor Drive has begun and will be complete by the end of this week. Next week repair of the roadway base will occur on these streets. Also next week, spot curb repair and replacement on Park Boulevard will continue.

May 8


All traffic exiting from eastbound I-290 will move onto 1 ramp. Work is scheduled to begin after 10 p.m. on May 8, reducing the number of lanes on a section of westbound IL Route 390 (Thorndale Avenue). All traffic exiting to IL Route 390 from eastbound I-290 will be moved onto 1 ramp to continue construction of the new flyover ramp that will connect westbound I-290 to IL Route 390.

On IL Route 390, westbound traffic will be reduced to 2 lanes near the exit to eastbound I-290. The outside westbound lane will serve as an exit only lane to I-290. The IL Route 390 lane reduction will be in place for about 2 months.
 
In addition, a portion of the ramp carrying traffic from eastbound I-290 to IL Route 390 is scheduled to close later this week for construction. The existing eastbound I-290 to eastbound IL Route 390 ramp will be widened and all vehicles exiting eastbound I-290 onto IL Route 390 will continue to the same traffic signal with westbound traffic directed to turn right and eastbound traffic directed to turn left. Up to 10,500 vehicles a day use the segment of the ramp serving only westbound IL Route 390 . Up to 18,000 vehicles a day use the combined ramp.

The lane reduction on IL Route 390 and the ramp closure are needed to provide a work zone for construction of the new interchange connecting IL Route 390 and I-290. This year, 8 piers will be built for the flyover ramp as part of the I-290 Interchange Project. Beam placement for the flyover ramp is expected to begin later this year and be complete in spring 2015. Work will also begin on the new ramp connecting westbound I-290 to eastbound IL Route 390, but that work will have no immediate impact on traffic.
The I-290 Interchange is being reconstructed to provide direct access to and from IL Route 390 in all directions.

May 7


Elgin O’Hare- On the south side of the Devon Ave Bridge IDOT will be constructing abutments and relocating utilities. At the I-290 interchange they will be constructing piers, performing layout and construction of posts for the proposed Noise Wall. There will be lane configuration changes within the week. Thorndale Ave. (I-390) construction will continue ongoing widening and construction on the Noise Wall. Rohlwing Road (Rt 53) landscaping will continue. Piers and abutment will begin to be installed.
 
In the Hamilton Lakes area surface grading will begin. Curb and gutter removal and replacement will continue. The storm sewers will be modified. At Park and Pierce changeable message signs are up and construction will begin today. Curb and gutter work will begin later this week.
 
Contractor(s) in general are within the currently projected schedule

May 2


As a reminder, next week spot curb repair and replacement begins on Park Boulevard in the Hamilton Lakes area. Off peak, daytime lane closures in both directions on IL Route 390 / Elgin O’Hare between Meacham Road and Roselle Road are also scheduled for the week of May 5. Please use caution at all times.

April 29


The Illinois Tollway will start work this week to being building the IL Route 390 mainline. Weather permitting, work is scheduled to shift traffic on the Elgin O’Hare Expressway between Meacham Road/Medinah Road and Rohlwing Road to create a work zone for roadway reconstruction. Overnight lane closures will be necessary to complete pavement striping and to shift traffic. Lane reductions will be removed by 5 a.m. daily in advance of the morning rush hour.

Eastbound traffic will be shifted to the left for several weeks to allow for the rebuilding and widening of the outside shoulder. When completed, eastbound and westbound traffic will then be shifted to the right and work will begin to rebuild the inside shoulders and lanes. Traffic is expected to remain in this configuration until late summer.

Once the traffic shift is on place, a 45 mph speed limit will be in effect 24/7 in the Elgin O’Hare construction zone, whether or not workers are present.

In the Hamilton Lakes area, resurfacing of Village streets is underway. Construction signage will be installed later this week for road work on Park Boulevard. Next week, the contractor will begin spot curb repair and replacement and curb drain structure repair on Park Boulevard. This process will take about 2 weeks, and then grinding of the asphalt will occur in mid-May. Spot curb repair and replacement and curb drain structure repair will also continue next week on Windsor Drive and Pierce Road.

Drivers should continue to watch for changing traffic patterns and use caution at all times.

April 28


One lane on the westbound of exit ramp from Thorndale Avenue to westbound I-290 will close from 7 a.m. to 4 p.m. on Tuesday, April 29, for camera work.

April 24


IL Route 53 / Rohlwing Road from Nordic Road / Bloomingdale Road to West Thorndale Avenue is scheduled to be opened to all traffic on Wednesday, April 30, weather permitting. The remainder of the work in Itasca for this project (such as parkway restoration, landscaping, etc.) is to be performed using daytime lane closures. Please watch your speed.

Overnight lane closures along I-290 and the existing portions of the Elgin O’Hare Expressway are expected this weekend for earth excavation, noisewall removal, and barrier wall installation. All lanes will reopen by 5 a.m. on Monday, April 27.

April 21


Multiple lane closures are expected this evening on the existing Elgin O’Hare, Thorndale Avenue, and I-290. All lanes will reopen for morning rush hour traffic:

One eastbound lane of the existing Elgin O’Hare between Roselle Road and Meacham Road will close at 8 p.m. tonight, April 21, for noisewall removal and earth excavation. One westbound lane will close at 9 p.m. for earth excavation. The eastbound lane will reopen by 5 a.m. on Tuesday, April 22. The westbound lane will reopen by 6 a.m.

One westbound lane on I-290 at Devon Avenue will close at 7 p.m. tonight, April 21, for bridge beam removal. A second lane will close at 9 p.m. and a third at 11 p.m. In addition, there will be full closures of 15-minute durations beginning at 1 a.m. and ending by 5 a.m. on Tuesday, April 22. All lanes will reopen by 5 a.m.

The entrance ramp from eastbound Thorndale Avenue to westbound I-290 will close just before midnight tonight, April 21, for bridge beam removal. The ramp will reopen by 5 a.m. on Tuesday, April 22.

The exit ramp from westbound I-290 to Thorndale Avenue will close from 8 p.m. to 9 p.m. tonight, April 21, for electrical installation.

The entrance ramp from westbound Thorndale Avenue to westbound I-290 will close from 9 p.m. to 10 p.m. tonight, April 21, for electrical installation.

The entrance ramp from westbound Thorndale Avenue to eastbound I-290 will close at 11 p.m. tonight, April 21, for electrical installation. The ramp will reopen by 5 a.m. on Tuesday, April 22.

One eastbound lane between Devon Avenue and Thorndale Avenue will close from 7 p.m. to 9 p.m. tonight, April 21, for electrical installation. During that time, the exit ramp from eastbound I-290 to westbound Thorndale Avenue will close.

One eastbound lane on I-290 between Biesterfield Road and Thorndale Avenue will close at 9 p.m. tonight, April 21, for electrical installation. A 2nd lane will close at 10 p.m. and a 3rd at 11 p.m. All lanes will reopen by 5 a.m. on Tuesday, April 22.

April 19-20


Overnight lane closures are scheduled for late Sunday, April 20 into early Monday, April 21 for noisewall removal and earth excavation along the existing Elgin O'Hare Expressway.

One westbound lane between Meacham Road and Roselle Road will close just before midnight on Sunday. One eastbound lane between Roselle Road and Plum Grove Road will also close. The eastbound lane will reopen by 5 a.m. on Monday. The westbound lane will reopen by 6 a.m.


April 18


Please note that next week construction will begin within the Hamilton Lakes development. On Windsor Drive and Pierce Road, contractors will be marking portions of curbing for removal and then begin the removal process of those sections. Spot lane closures may occur during the day.

April 17


One eastbound lane on I-290 at Devon Avenue will close at 7 p.m. tonight, April 17, for bridge beam removal. A 2nd lane will close at 9 p.m., a 3rd at 11 p.m. and a 4th at midnight. In addition, there will be full closures of 15-minute durations beginning at 1 a.m. All lanes will reopen by 5 a.m. on Friday, April 18.
 
One westbound lane on I-290 between Irving Park Road and Thorndale Avenue will close at 7 p.m. tonight for electrical installation. The lane will reopen by 5 a.m. on Friday, April 18.

Three eastbound lanes on I-290 between Thorndale Avenue and Devon Avenue will close at 11 p.m. tonight for electrical installation. In addition, the eastbound entrance ramps from Thorndale Avenue will close at midnight. All lanes will reopen by 5 a.m. on Friday, April 18.
 
One eastbound lane of the Elgin O’Hare between Meacham Road and Roselle Road will close at 8 p.m. tonight for pavement patching. One westbound lane will close at 9 p.m. for noisewall removal and pavement patching. The eastbound lane will reopen by 5 a.m. on Friday, April 18. The westbound lane will reopen by 6 a.m.

April 15


Overnight and daytime lane closures are scheduled for noisewall removal, earth excavation and temporary traffic signal installation.

On Thorndale Avenue, 1 lane in each direction between Meacham Road and Roselle Road will close at 9 p.m. tonight, April 15, for noisewall removal and earth excavation. All lanes will reopen by 5 a.m. on Wednesday, April 16.

One lane on the entrance ramp from eastbound I-290 onto Thorndale Avenue will close from 9 a.m. to 3 p.m. on Wednesday, April 16, for electrical installation.

April 14


Overnight and daytime lane closures are scheduled for noise wall removal and temporary traffic signal installation.

Overnight 1 westbound lane of Thorndale Road / Elgin O’Hare between Meacham Road and Plum Grove Road will close at 9 p.m. for noisewall removal. The lane will reopen by 6 a.m. on Tuesday, April 15.

On Tuesday, April 15 1 westbound lane of Thorndale Road between IL Route 53 / Rohlwing Road and Park Boulevard will close from 9 a.m. to 3 p.m. for temporary traffic signal installation

April 11


Overnight and daytime lane closures on Thorndale Avenue and I-290 are scheduled for the weekend for pavement sawing and an equipment move.

On Saturday, April 12, 1 westbound lane on Thorndale Avenue between Meacham Road and Roselle Road will close from 5 a.m. to noon for pavement sawing. One eastbound lane will close from 5 a.m. to 8 a.m. One westbound lane between Meacham Road and Roselle Road will close from 5 a.m. to 2 p.m. on Sunday, April 13, for pavement sawing. One eastbound lane will close from 5 a.m. to 10 a.m.

One eastbound lane on I-290 between Biesterfield Road and Thorndale Avenue will close at 7 p.m. on Sunday, April 14, for an equipment move. A 2nd lane will close at 9 p.m. and a 3rd at 11 p.m. In addition, there will be 1, full closure of a 15-minute duration beginning at 3 a.m. All lanes on I-290 will reopen by 5 a.m. on Monday, April 14.

April 8


Overnight lane closures are scheduled for noisewall and barrier wall installation.

October 29


GroundbreakingDue to weather, the newly constructed ramp from eastbound I-290 to eastbound Illinois Route 390 that was scheduled to open this Tuesday has been postponed until Wednesday, November 30th at 1:00 am. The left lane will remain closed to be opened at a later date. In conjunction with the ramp opening, the traffic signal at the existing intersection of the ramp from eastbound I-290 to eastbound Illinois Route 390 will be removed. Additionally, third lane on westbound Illinois Route 390 between Hamilton Lakes Drive and I-290 will be opened. Please use caution when driving in construction zones.